I created a multiple smaller projects that I am attempting to add to a master project. When I add the subprojects and insert a % complete column some of the subproject percentages are not showing the accurate percent complete. How can I fix this?
Ensure that the percent complete calculation method is set correctly for your project. Go to Project > Project Options > Earned Value and verify that the calculation method is set to Percent Complete