Hello,
 
I created a multiple smaller projects that I am attempting to add to a master project. When I add the subprojects and insert a % complete column some of the subproject percentages are not showing the accurate percent complete. How can I fix this?
  • Suggested answer
    VaHiX Profile Picture
    VaHiX 3,323 on at
    MS Project Sub Project Issue
    Ensure that the percent complete calculation method is set correctly for your project. Go to Project > Project Options > Earned Value and verify that the calculation method is set to Percent Complete
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Verified Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,431 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,503 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans