Copy the Work Schedule on Different Days on Calendar

(1) ShareShare
ReportReport
Posted on by 30

Hello, 

Is there a way to copy the Work schedule on the Calendar module for the generated days on a specific calendar

pastedimage1626937675876v1.png

When I tried to select the other days the work schedule also changes and goes back to the default value. 

pastedimage1626937723025v2.png

I wanted to copy the specified work schedule to all days in a specific Calendar. 

I really appreciate if there's a better way to do it. Thanks in advance.

  • Suggested answer
    C. Shenk Profile Picture
    Microsoft Employee on at

    Hello Nathaniel,

    Thank you for your question - are you attempting to copy individual days working times to other individual days with the "Days" pane under the Working Time Calendar? For example I have 1/1/2021 highlighted here where I have a schedule of 12 a.m. to 24:00 (just for the example):

    pastedimage1627592580995v1.png

    But then if I switch to the next working day, 1/11/2021, it will take the default time that was used at generation, 8 a.m to 5 p.m 

    pastedimage1627592649020v2.png

    If I am understanding correctly, you would want to copy from one individual day, to multiple other individual days within the same calendar? 

    While there is no 'copy' function per se, one direction you may be able to pursue is to regenerate the working times for the days in question, dividing the working time using the non-working time function. When entering in the range of days, the system will prompt once with the warning.

    pastedimage1627593167029v3.png

    If the non-working times are set correctly (for example here I have an 8 - 6 shift with an hour for lunch) it should break apart the workday accordingly: 

    pastedimage1627593273270v4.png

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the August Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 515 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 417 Super User 2026 Season 2

#3
CU10121822-0 Profile Picture

CU10121822-0 360

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans