I have some 50 tasks under a case. I want to show at case level (either through view or dashboard), if there is any bottleneck in the case progress, means i need to show which task are not completed. I need to show at case level.
Thanks
Hi Nagarajan,
Please follow the stages:
1. Create a new view which filter the activity type is open on the Task entity. You can add some columns you need. Then save and publish it.
2. Open your case form, add a subgrid component. Set the subgrid like the following screenshot:
Result:
Open a case record and you could see all the uncompleted tasks:
You should check out new Task Management solution for Dynamics 365. It contains of 3 custom dashboards:1. My Tasks2. Tasks by User3. Tasks by Project (this one can be modified according to your business need, for example Tasks by Cases).
Dashboards are easy-to-use and allow you to manage all your tasks in one place, regarding to the specific Dynamics 365 record and to track progress on the Case development. You can also monitor the due dates and tasks priorities or break tasks down into sub-tasks.
The solution is available on AppSourcehttps://appsource.microsoft.com/en-us/product/dynamics-365/skyline-consultants-5228552.skyline_taskmanagement?tab=Overview,
or you can visit Skyline Consultants website for more detail:https://skylineconsultants.com/task-management/
Best,Kristina
[View:/cfs-file/__key/communityserver-discussions-components-files/763/4.-User-friendly-Dashboards.mp4:320:240]
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Muhammad Shahzad Sh... 69 Most Valuable Professional
Daniyal Khaleel 25 Most Valuable Professional
Ayesha Wajahat 16