Dampener Period & Dampener Qty.

(0) ShareShare
ReportReport
Posted on by

hello, how can i use dampener Qty. and dampener period with example please.

with appreciation

*This post is locked for comments

  • Suggested answer
    Inge M. Bruvik Profile Picture
    1,025 Moderator on at
    RE: Dampener Period & Dampener Qty.
    [quote user="VELTUFF"]

    Using the dampener Qty, does it takes already purchase orders in consideration when using fixed reordering?

    [/quote]

    Yes, it should - that is definitely my understanding.

  • VELTUFF Profile Picture
    90 on at
    RE: Dampener Period & Dampener Qty.

    Using the dampener Qty, does it takes already purchase orders in consideration when using fixed reordering?

  • Suggested answer
    Paras mehan Profile Picture
    3,518 on at
    RE: Dampener Period & Dampener Qty.

    Hi,

    Dampener Period: Specifies a period of time during which you do not want the planning system to propose to reschedule existing supply orders forward. The dampener period limits the number of insignificant rescheduling of existing supply to a later date if that new date is within the dampener period. The dampener period function is only initiated if the supply can be rescheduled to a later date and not if the supply can be rescheduled to an earlier date. Accordingly, if the suggested new supply date is after the dampener period, then the rescheduling suggestion is not blocked. This field is enabled if Reordering Police is set as Order or Lot-for-Lot.

    If the lot accumulation period is less than the dampener period, then the dampener period is dynamically set to equal the lot accumulation period. This is not shown in the value that you enter in the Dampener Period field.

    Dampener Quantity: Specifies a dampener quantity to block insignificant change suggestions for an existing supply if the quantity by which the supply would change is lower than the dampener quantity. If the suggested change in quantity is higher than the dampener quantity, then the suggestion is not blocked. If this field is empty, then the value in the Default Dampener Quantity field in the Manufacturing Setup window applies.

    This field is disabled if Reordering Police is set as Order.

    Hope this helps.

    Best Regards,

    Paras Mehan 

  • Community Member Profile Picture
    on at
    RE: Dampener Period & Dampener Qty.

    in the item card, there are tow fields in the planning fast Tap, Dampener QTY and Dampener Period, they work differently with reordering policy types. 

  • Suggested answer
    Stefano Demiliani Profile Picture
    37,166 Most Valuable Professional on at
    RE: Dampener Period & Dampener Qty.

    What do you mean by Damperer Qty?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge Winners! 🌸

Congratulations to all our community participants!

Adis Hodzic – Community Spotlight

We are honored to recognize Adis Hodzic as our May 2025 Community…

Kudos to the April Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard > Microsoft Dynamics NAV (Archived)

Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans