Hi All,
We have unapproved revisions showing on a project budget. This project went through the workflow for 'original' budget, but not for the revision?
Recall is not an option. User does not think these 'unapproved' amounts should be there.
The attached screen shot shows the costs tab of the project budget.
My understanding is that the project budget, when originally set, goes through the 'original budget workflow' (wf#12 for us; this looks good). Then, when revisions are made, it should go through the 'revision workflow' (our wf#3). I see no sign that the revision workflow was initiated.
Please advise.
Hi ASidd,
Please be more patient to wait answers from others on the forum.