Skip to main content

Notifications

Announcements

No record found.

Microsoft Dynamics AX (Archived)

Internal project immediate consumption and expenses

Posted on by 15

Hello everyone,

 In AX 2012 R3 We have the following 2 issues with receptions and consumption in project POs:

 

1. In an Internal Project, on every PO Product reception, items are always “immediately consumed”. No question "Consume items for the project immediately" asked.

2. That immediate consumption doesn't update project expenses. Rather, the items stay in an "Deducted" state in Inventory, and expenses are updated when the invoice arrive. Which is standard behavior as I've read.

 

Questions:

  • Where do I configure an internal Project to ask if I want to consume immediately on reception? 
  • What may I do to force expenses updates on those items that are in “Deducted” state? We can’t wait for the invoices.

Thanks in advance.

Alfredo.

*This post is locked for comments

  • Verified answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Internal project immediate consumption and expenses

    Hi dig41,

    For the internal Project you cannot do anything else than waiting for the invoice to arrive.

    You already found an alterntive; that is, using a time & material project type instead. This seems to be the better option from my perspective.

    Best regards,

    Ludwig

  • dig41 Profile Picture
    dig41 15 on at
    RE: Internal project immediate consumption and expenses

    Thanks, Ludwig, that's a complete answer.

    A couple of related questions.

    Since is an internal Project, we have several item transactions  waiting the invoices to update Project expenses. May we do something to update for those transactions before invoices arrive? May be a temporary expense record, something similar.

    To avoid this problem, is possible to change "on the run" these projects type from "Internal" to "time and material"?

    Thanks again.

    Alfredo.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Internal project immediate consumption and expenses

    Hi Alredo,

    Please have a look at the following LCS description:

    Solution 704755Product Receipt not creating Project Consumption

    The reason that you are not seeing the transaction is that you are not using an item requirement. The only way that the item consumption will post at time of receipt is if the item requirement is created. The item requirement can be created manually and then the purchase order created from the item requirement. Or if the you have ‘Create item requirement’ option marked, the item requirement will be created automatically in the background with the purchase order/receipt.

    If you use internal projects you cannot create an item requirement and no sales order that is required by the item requirement. Therefore it works as you describe it for your internal projects and there is no parameter or setup that would change that.

    Note: If you just want to see the costs earlier at the Project Level you could activate the respective committed costs parameters as a workaround.

    Best regards,

    Ludwig

  • dig41 Profile Picture
    dig41 15 on at
    RE: Internal project immediate consumption and expenses

    Hello Ludwig,

    We already have the configuration you mention. And its working fine (asking in every reception) for all projects.

    We have problems only with   internal projects that don't ask, and consume immediately everytime.

    Is a this a behavior specific for internal projects? Could I change it?

    Thanks,

    Alfredo.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Internal project immediate consumption and expenses

    Hi Alfredo,

    Question 1: In the Project Parameters (General tab) there is a parameter 'create item requirement'. Activating this one will make the pop up available and ask you whether you want to consume the items immediately.

    Question 2: If you want to post the expense immediately with the packing slip posting you activate in Addition to the 'create item requirement' Parameter, the 'item consumption' parameter. Activating this second parameter will not ask the users whether or not they want to consume the items and let them decide by chosing yes or no but rather automatically consume the items without asking the user.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans