We are using AX 2012 R3 CU8, wondering if there is a way to calculate how long the total lead time is required for a production build with multiple assemblies. I.e. There is a part with 5 sub-assemblies with each assembly taking a different amount of time. Within those sub assemblies there are items with dates that vary from 1 day to 200 day lead times. If all items and BOMs are set up with a correct lead times, is there a way to simulate how long it will take to deliver?
*This post is locked for comments
I have the same question (0)If item is on a sales line you can run the CTP (Capable to Promise) delivery date control and that would get you the estimated delivery date based on the lead time of a BOM item, machine capacity etc.
If you created a manual production order for an item, you need to estimate the order and run the explosion and that will do the same as CTP.
Alternatively, you can create a manual planned production order for an item.