job scheduling with resource groups

(0) ShareShare
ReportReport
Posted on by Microsoft Employee

We have a resource group (MG1) that included 6 different resources (M1, M2, M3, M4, M5, M6), all capable of performing the same work. All of them are set to infinite capacity.

Just recently, we have decommissioned 2 of the 6 presses and have removed them from the resource group. Now the resource group includes M3, M4, M5, and M6.

Our routes and production routes use the resource group (MG1) as the requirement type, so that when we run job scheduling, the scheduling engine selects one of the resources in the group.

Since we removed M1 and M2 from the group, we have not been able to schedule the production orders. We get an error message that there isn't enough capacity. It almost seems as if it is still trying to schedule to either M1 or M2. If I add M1 and M2 back into the resource group, the production order can schedule without problem.

I tried putting an expiration date on the resources in the resource groups, hoping that scheduling would look at the next open date on a different resource, but that did not seem to help. I tried assigning a new calendar with zero working hours to the decommissioned resources, but that did not help either.

Does anyone have an idea on where I should start looking next or what else I can try?

*This post is locked for comments

  • Suggested answer
    guk1964 Profile Picture
    guk1964 10,877 on at
    RE: job scheduling with resource groups

    This post by Evert covers it www.sikich.com/.../

    see points 1 and 5

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: job scheduling with resource groups

    Hi all, 

    i have the same problem  with the job planning to visualize the Gantt chart. In fact, the problem appears only when i use a resource of type resource group or other than type resource you find bellow the error message attached

    75018.Capture.PNG

    best regards

  • Suggested answer
    B S FARTIYAL Profile Picture
    B S FARTIYAL 445 on at
    RE: job scheduling with resource groups

    After Removing the M1 and M2 the resource group capacity is reduces as per production requirement, if you still remove the m1 and m2 , increase production quantity in operation with in time otherwise include more resource, its depending your production  quantity and delivery and available resource capacity.

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: job scheduling with resource groups

    Thanks for the response. We do have both job and operations scheduling boxes checked, but the issue remains the same.

  • zqr Profile Picture
    zqr 850 on at
    RE: job scheduling with resource groups

    Try this and see if it helps. Go to the route of that production order, then go to the operation number that is showing the error, and in the resource requirements tab make sure Operations scheduling and Job scheduling check boxes are checked.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Verified Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,391 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,445 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans