Excess Pick Of Material need to reduce picked qty, from Component

Posted on by Microsoft Employee

Hi Blog members,

My company is using Warehouse Module. I have registered certain qty. of pIck for a Prod, Order but by mistake pick generated was of excess qty. So is there any way to rectify linking that Prod. order as well. I tried using Movement worksheet but the Picked qty in Prod orders remained same.

Thanks And regards

Harsh Manglani

*This post is locked for comments

  • Suggested answer
    Alex A Profile Picture
    Alex A 2,348 on at
    RE: Excess Pick Of Material need to reduce picked qty, from Component

    Harsh, I found some further information on this. The answer to my own questions about this process was found at this link:

    www.olofsimren.com/reversing-production-output-and-consumption

  • Alex A Profile Picture
    Alex A 2,348 on at
    RE: Excess Pick Of Material need to reduce picked qty, from Component

    Hello, did you say that you had already registered the Pick? Do you see items in the "Qty. Picked" column of Prod Order Components screen?

    6507.tempdelete.png

    6507.tempdelete.png

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Excess Pick Of Material need to reduce picked qty, from Component

    Hi Alex,

    I got the first point about movement but I am not sure about second one. In second point you have mentioned that I should change the consumption quantity. Here I want to make a point clear that I have not consumed anything yet so if  I will replace the quantity with negative figure system  will not reverse the effect of consumption as no consumption is posted yet.

     Thanks And Regards

    Harsh Manglani

  • Alex A Profile Picture
    Alex A 2,348 on at
    RE: Excess Pick Of Material need to reduce picked qty, from Component

    Hi Harsh,

    I'm still figuring this out but it could require two steps. Or, it may only require the second step below (using the Production Journal or the Consumption Journal). I will be doing more testing on this later this week.

    1.) Use the Movement Worksheet to move the items out of WIP and back to their Raw Material Bin locations. This is for the physical inventory side.

    2.) Use the Production Journal (from the "Line" drop down at the top of the "Lines" section of that same Production Order) and put a negative amount for the Consumption Quantity for the amount to be returned for each of the Raw Material components you would like to "un-pick" from that Production Order. NAV will let you put a negative consumption quantity for the financial side.

    Please let me know if this provides the expected result.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,235 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans