Posted on by 108

Hello everybody, I'm trying to generate a rework order, I'm following the manual step by step, the only difference I have is that my products doesn't have the need of routes, there are no routes created neither required so I don't select any route for the rework. Im doing the manual reserve of the lot to be reworked, but after that neither the Release nor the Start buttons are activated, they remain deactivated as if there is a step missing. I also created a fake route, with one operation in order to do the Schedule operations step to see if this was the problem, but no changes... any help/suggestions?

Thanks a lot,

Kapil

*This post is locked for comments

I have the same question (0)
  • Weaveriski Profile Picture
    23,620 Moderator on at

    What status is the order? created?

    Which manual and which page?

    Your product has a technical need for routes if you are going to do any rework?

    In production parameters what statuses can you move between?

  • kaps Profile Picture
    108 on at

    HI Steven, 

    The thing is in batch order manual reservation is not happening and hence it is not allowing me to start.

    one more thing is my item is a CW item, does that have any affect on in...  

    I am refering  the ms pdfs for students AX2012_ENUS_PMI_03 >> rework batch order 

  • Weaveriski Profile Picture
    23,620 Moderator on at

    What do you mean manual reservation is not happening; manual reservation means there is none, unless you do it. Reservation prevention has nothing to do with moving on the status of the production order, but in a rework order you estimate the works order and then reserve against the RAF order that produced the original goods you are reworking, and the BOM you add is the item itself.

    Have you created a BOM with the item containing itself?

    Is the status of the original production order you are re-working at RAF?

    Is the item you are reworking in stock for you to rework?

    What is the current status of your order?

    Have you manually reserved the original? I guess not from your comment, but why not?

  • Suggested answer
    Community Member Profile Picture
    on at

    The production order has to be estimated and route is mandatory for network. Associate a route and estimate, and job & operation scheduling the PO then it will be activated 

    Thanks 

    Tarun 

  • Verified answer
    kaps Profile Picture
    108 on at

    HI Experts,

    Since the we have only defined  the “inventory batch attributes per product”, so the system was considering the batch with attribute value for reservation and ignored others.

     

    Thanks all for your help..

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans