Hi,
We're looking to implement the Absence Manager functionality in Dynamics HR for a subset of staff who need to have their leave approved by a resource manager rather than their line manager.
When we set up the Absence Manager do we need to add all staff to the new hierarchy, even if their leave is still to be approved by their line manager? Trying to avoid the overhead of managing and maintaining that if I can.
Thanks,
Rob
Hi Rob,
This functionality is developed based on Leave and absence parameters > Absence hierarchy.
docs.microsoft.com/.../hr-configure-absence-manager
yes you need to add manager's position in relationship for all the staff as you're using custom hierarchy. Better you export/import data from data entity in case where your line manager and absence manager is same for multiple positions.
Regards,
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 495 Most Valuable Professional
André Arnaud de Cal... 432 Super User 2026 Season 2
CU10121822-0 366