Hi Expert,
I get some question on here hope someone can help solve it.
Sample.
Example :
Below is my formula screen shot.
YPFIN-1( Finished good) get a sales order for 1000 ctn, to produce 1000 ctn of YPFIN-1 i need R1(Raw Material 1) 1000kgs .
Assume:
R-1=10 kgs per ctn ( Inventory unit = ctn)
R-2=8 kgs per ctn ( Inventory unit = ctn)
Scenario 1. If both item was 0 on-hand quantity, after run master plan system propose to purchase 100 ctn for R-1( correct).
Scenario 2. Now R-2(alternative item) had 10 ctn on-hand. After run master plan, system propose to purchase 90 ctn for R-1 mean 900kgs, result was not we expected.
Supposed R-2 10 ctn = 80kgs, 1000kgs-80kgs=920kgs, system should propose to purchase 92 ctn(920kgs).
Current i face this issues anyone can give a suggestion how to solve this.