Hi all, i wonder if it is possible to get National Holidays visible or pre-filled in the workers Timesheet, organization wide?
Hi Leonardu,
Yes, any holidays you include in Business closures can be referenced on every user’s calendar if you set it up correctly.
In the Power Platform admin center, under settings, click on Business > Business closures. Once that opens on another tab create your national holiday.
Then inside Resource, navigate to Work Hours, then inside one of them > Edit > Select All events in the series > Toggle Observe Business Closure to ON.
Important: You must toggle it to ON inside every resource you want that to happen.
Hope this helps, please mark it as answered to help others.
Thanks,
www.d365hacks.com
Also, in order to update many resources in one shot, you can use the XRM Toolbox, Home · XrmToolBox, the tool: Bulk Update Work Hours. This would create a holiday in each resource's calendars.
The other way is through an API. Hope this helps, please mark it as answered to help others.
Hello Juan, tnx for your reply!
i did like you suggested, and now the National Holidays are visible in the working hours.
maybe you know a way to get them in draft in the Timesheets as well, for the whole next year?
(so the time writers cannot forget them when they are entering their time in their Timesheets)
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 503 Most Valuable Professional
André Arnaud de Cal... 434 Super User 2025 Season 2
BillurSamdancioglu 278 Most Valuable Professional