Hello Everyone
I have some queries related to project accounting in Microsoft Dynamics GP
We have create the project below in GP
Project Fee = 1,543,484
I have made two bills one for 70% of fee amount = 1,080,438 BILL0000000000077
and second bill for =463,046 BILL0000000000157
I have voided second bill for =463,046 BILL0000000000157 from project accounting receivable bill but project still show that value in billing to date
also if i want to re bill in that project i doesn't allow me to bill in that project it still shows complete project has billed.
How can i correct it and re bill the remaining amount in that project.
I have run checklinks and reconcile as well but error still stands there.