Hi, I have discovered following strange behavior:
OK thanks I have voted for that, but this definitely needs improvement. I consider this a bug and not a feature.
Forgot to login before answering...
When you approve a time-off request, it updates the resource's working hours. However this only works one-way, i.e. if you delete the time-off it will not affect the work hours and the area in the Gantt chart remains grayed out.
There is already an enhancement suggestion that needs more votes: experience.dynamics.com/.../