If we want to delete or retire a resource from a project (Knowing that a linked expense report is already posted and paid in the project), How can we do this? And if we did it, what is the impact : Do we loose all the past history of all actual hours booked by the resource?
Please could you help me with this?
Thank you in advance,
Hi Ahmed,
2 ways to remove resource from a project. If we remove resource it will not impact past transactions, this change will apply to future transactions only.
1) From project master-go to resource assignment-unselect the resource
2) From worker-go to project tab-assign projects-unselect the project
Hello, Kumar,
I tested that, first I assigned a resource to a project then created a timesheet (status in review) then unassigned the resource and I checked the transactions in the project, and I found the timesheet submitted linked to the resource in the pending transactions.
Thank you so much for your answer and your time,
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
CA Neeraj Kumar 2,047
André Arnaud de Cal... 885 Super User 2025 Season 2
Sohaib Cheema 592 User Group Leader