Scheduler board which takes into account the work hour template of the work order

(0) ShareShare
ReportReport
Posted on by 60
Hello,
 
It's possible on a work order to add a /Work Hour Template/.  
In the scheduler Board, I would like that when assigning a work order, the system proposes the available resources while taking into account the availability of the /Work Hour Template/ associated with the WO.
I checked in the scheduler Board setting, but this query isn't standard. Is it possible to adapt one of them to take care of it ? 
 
Thanks in advance ! 
 

//
 
 
I have the same question (0)
  • RudyZhang Profile Picture
    Microsoft Employee on at
    Hi,
     
    Our team analyzed your problem and based on the information you provided, our team thinks you may need to switch query or customize query
     
    You can switch the query by following these steps
     
    Step1, go to Field Service and select Schedule Board.
     
    Step2, click Settings button, click All Board Settings, click Edit Defaults.

    Step3, click Work Order tab and select the query you want to modify.

     
    If you want to write customized query, please refer to this document in the link below.
    Schedule Board Extensibility in Microsoft Dynamics 365 Field Service - Microsoft Dynamics 365 CRM Tips and Tricks (inogic.com)
     
     
    I hope my answer is helpful to you! If you have any other questions, please feel free to contact me.
     
    Best Regards,
    Rudy Zhang
  • Suggested answer
    Gabriel Dias Junckes Profile Picture
    2,428 on at
    Assigning the Work Hour Template to the Work Order will set the resource requirement calendar with the time zone and availability. 
     
    The Schedule Assistant matches the requirement and resource availability to bring the resource availability slots.
     
    However, Field Service will only set the Resource Requirement Calendar on the Work Order creation, so the calendar won't be changed if the Work Hour Template is updated. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Service | Customer Service, Contact Center, Field Service, Guides

#1
Tom_Gioielli Profile Picture

Tom_Gioielli 55 Super User 2025 Season 2

#2
Daniyal Khaleel Profile Picture

Daniyal Khaleel 27 Most Valuable Professional

#3
Scott Jackson UK Profile Picture

Scott Jackson UK 22

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans