Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Suggested answer

Not able to add Project Planned Cost into the project task

(1) ShareShare
ReportReport
Posted on by 17

Hello Everyone I am new to PSA and I am just trying to add Planned Cost for the scheduled task but I am not sure where should I put that one. As of now, I am directly trying to add it into the schedule section where we add start/end date, duration but when I add planned cost in that one and refresh the page Planned cost is not showing on Otherside all other information(start/end date, duration ) is still there.

For more understanding I have attached a screenshot of the place where I am trying to add planned cost so please have a look and let me know where I should add that cost?

Thanks in advance7506.Screenshot-2022_2D00_03_2D00_18-155350.png

  • Suggested answer
    Matthew Lazowski Profile Picture
    Matthew Lazowski 3,163 on at
    RE: Not able to add Project Planned Cost into the project task

    It may be worth getting familiar with training materials on how to do this: docs.microsoft.com/.../5-sales-management. It is for PSA 4.0 (aka Project Operatrions) but it is similar in PSA 3.x also.

  • Suggested answer
    Nya Profile Picture
    Nya 29,058 on at
    RE: Not able to add Project Planned Cost into the project task

    Hi,

    Initially on the task creation: Planned cost will be set to the Estimated cost at complete. Once Actuals are recorded on the task, the following will be calculation on the Tracking view for Effort

    • Progress percentage = Actual effort spent to date ÷ Estimate at complete (EAC)
    • Estimate to complete (ETC) = Estimate at complete (EAC) – Actual effort spent to date
    • EAC = Remaining effort + Actual effort spent to date
    • Projected effort variance = Planned effort – EAC

    Project Service Automation shows a projection of the effort variance on the task. If the EAC is more than the planned effort, the task is projected to take more time than was originally planned. Therefore, it's behind schedule. If the EAC is less than the planned effort, the task is projected to take less time than was originally planned. Therefore, it's ahead of schedule.

    For more details, please refer to the following documentation:

    Project cost tracking | Microsoft Docs

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 292,516 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,407 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans