Hi,
I've experienced following issue. There is one open (not already planned) Work Order. I plan it on the Schedule Board for the team A but not for the complete Work Order Time (e.g. complete Work Order Time = 4 hours, but for the team A it is planned only for 3 hours). For the remaining time (1 hour) I try to plan an additional user B which is not a member of the team A. After dragging the Work Order to the Schedule Board and assigning it to the user B I get following warning:
Cannot set Crew Member Type for a Bookable Resource Booking which was not booked as part of a Crew.
Does anybody of you have an idea about this warning?
Regards,
Mark
Hi Mark.
I haven't tried to do your scenario.
You can create another resource requirement on the work order with one hour to schedule resource B.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Tom_Gioielli 45 Super User 2025 Season 2
Daniyal Khaleel 27 Most Valuable Professional
Soundari 15