Why can the end user not specify a Job Number on a "Resource" line item of a Purchase Invoice?
Thanks!
John
Hello,
If you don't get further responses to this issue, you may want to raise a support request to Microsoft support via your CSP / Partner.
Thanks. Hopefully, someone will respond. :)
Hi,
That's because you are supposed to get the resource cost from time sheets.
If you specify job No. and task No. in the invoice then you're going to post the cost twice.