Project Budget for Non-Stock Item

Posted on by 75

Dear Member,

Please help to understand the system behaviour for Non-Stock item in Project budget.

Scenarios - we have fixed priced project for that we have project budget

we created purchase order from Item requirement for Non- Stock item ----> Purchase receipt ( At the time of purchase receipt system consumed the budget) ---> post purchase invoice ( At the time of invoice system again consumed the budget) . for same Item and same PO system consumed the budget twice. 

Can any one help to explain the reason why system consumed budget twice. how we can correct   

*This post is locked for comments

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Project Budget for Non-Stock Item

    Hi kumar,

    I noticed that there are some hotfixes available on LCS that are not even included in CU13.

    Tipp: Get a hold on a developer who can take a look at the issue and asses, which of the hotfixes might overcome the problem.

    If he/she does not find a suitable fix then you can either open a support case or try to fix the problem yourself with a code modification depending on the urgency of this matter.

    Best regards,

    Ludwig

  • kumar.tripathi Profile Picture
    kumar.tripathi 75 on at
    RE: Project Budget for Non-Stock Item

    Thanks for reply, We are using AX2012R3 CU13

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Project Budget for Non-Stock Item

    Hi kumar,

    You are right. This does not seem to be correct.

    What AX2012 version do you operate?

    If you are running an older one check LCS for available hotfixes.

    There are many available for project budgets.

    See e.g. fix.lcs.dynamics.com/.../Results;dm=0&v=3_5_7_4_1_16_15&i=2_1_3_4&ct=1_3_5_4_2_6&ft=1_2_3&cu=&pi=&pm=&pc=&rd=&d=&envId=&permission=&x=0&y=0

    Best regards,

    Ludwig

  • kumar.tripathi Profile Picture
    kumar.tripathi 75 on at
    RE: Project Budget for Non-Stock Item

    Thanks for reply, Issue is not with voucher AX is posting correct voucher.

     Let me describe the steps  what we did.

     Local Currency = SAR and PO currency – USD

     Exchange Rate – SAR= USD – 3.75

    1-    Select Non-Stock item with Cost price =35000

    Project-Budget-Balance-after-Receipt.png

    2-    Create Project Quotation and select the NON-Stock Item

    Project-Quotation.png

    3-    Quotation transfer to Project for that project we have Project budget =59,400

    1830.Project-Budget.png

    4-    We have created PO from Item Requirement, Purchase Price =15,000 USD

    5554.Item-Requirement.png

    Item-Requirement_2D00_PO.png

    5-    Post PO receipt

    PO-Receipt.png

    6- After Posting receipt system got consumed the budget

    Budget-Consumed-Error.png

    7-    After Posting an PO Receipt validate Budget Balance. ( System has consumed the budget from Quotation Cost )

    Project-Budget-Balance-after-Receipt.png

    8-    Post Purchase Invoice for USD 4050

    1212.PO-Invoice.png

    9-    After Invoice Posting validate Project Budget Balance ( System has consumed Twice )

    Project-Budget-Balance-after-Invoice.png

    Please review the screen shot and help us to solve this issue. We are getting this issue only for Non-Stock Item.

    Thanks for your help, wait for your reply.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Project Budget for Non-Stock Item

    Hello Kumar,

    The voucher that ends with 21839 is reversed in the voucher that ends with 21840.

    This is something I would expect AX doing.

    Where do you see the double counting?

    Best regards,

    Ludwig

  • kumar.tripathi Profile Picture
    kumar.tripathi 75 on at
    RE: Project Budget for Non-Stock Item

    Screenshot-2019_2D00_04_2D00_04-at-12.21.05-PM.png

    1780.Budget.png

    1780.Item-Requirement.png

    Screenshot-2019_2D00_04_2D00_04-at-12.21.05-PM.png

    4403.Receipt-Voucher.png

    4403.Invoice-Voucher.png

    As per your Suggestion, Please review the screen shot and can replicate the same. 

    Thanks for your help.

  • Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Project Budget for Non-Stock Item

    Hello kumar,

    I am interested in screenprints that show the project postings, the budget / consumed budget and the item transaction that consumed the budget twice.

    Would be great if you could upload those.

    Many thanks and best regards,

    Ludwig

  • kumar.tripathi Profile Picture
    kumar.tripathi 75 on at
    RE: Project Budget for Non-Stock Item

    Hi Ludwig,

    Thanks for reply, we are using AX2012R3, we have budget only for Project, for non stock item GL budget was there in 2018 but there is no GL budget in 2019.

    Which print screen should i need to share with you which can be relevant for your understanding.  

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Project Budget for Non-Stock Item

    Hi,

    It sounds strange that your budget is consumed twice. Can you share details and some screenshots?

    Also let us know the AX2012 version you operate and whether you use project budgets and/or ledger budgets.

    Many thanks

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,235 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans