Hi Team,
When i run the MRP on AX 2012, the suggestions doesn't consider on-hand inventory. I did read in the blog saying, we need to perform the below steps
1. Released items > plan action tab > net requirements > update master scheduling
Post doing the steps above, and rerunning the Master planning, the results are correct.
Do we have to do this for every item ? is there any setting i am missing ?
Thanks in advance !