Hi,
I have 2 resource with the same capability "Assembly". Resource 1 is given Priority 1, and Resource 2 is given Priority 2.
I create 2 Production Order that need capability Assembly. Both of the Production Order have same quantity and due date.
When I run the schedule job, both of the Production Order is using Resource 1 (with different starting time of course). Why does the second Production Order not using Resource 2? It doesn't make sense to me because Resource 1 is full at that time and Resource 2 is having no job at all. What setup do I need to make the second Production Order using Resource 2?
Thanks in advance