web
You’re offline. This is a read only version of the page.
close
Skip to main content
Community site session details

Community site session details

Session Id :
Microsoft Dynamics AX (Archived)

how to schedule multiple production resources on same operation to reduce lead time

(0) ShareShare
ReportReport
Posted on by

I'd like to set up AX2012 so that scheduling will automatically add a second machine resource to the current operation when the required hours exceeds the capacity of the primary resource.    In other words, minimize the lead time through production rather than stretch out the time using only one machine.   I've tried this using a seconadry operation but AX just runs the secondary op for the same hours as the primary....it doesn't split the hours across both machines and thereby cut the clock time in half.   Any thoughts?   

*This post is locked for comments

I have the same question (0)
  • Community Member Profile Picture
    on at
    Re: how to schedule multiple production resources on same operation to reduce lead time

    Have you tried setting up a resource group?  It's my understanding that if you have multiple resources doing the same function, you can combine them in a resource group, attach that group to the operation, and schedule capacity across the entire group.

  • Victor Pepi Profile Picture
    on at
    Re: how to schedule multiple production resources on same operation to reduce lead time

    Thanks for the input.  I have thought of what you are suggesting but it doesn't quite do what we need.   We've already put the resources into a group....but the job scheduling engine only chooses one of the resources and it will run it as long as needed to get the job done.   We'd like the scheduling engine to pick multiple resources, if available, so that the lead time is reduced.

  • Tony Barnes Profile Picture
    on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Hello Victor -

    On the Route > Resource requirements tab > Quantity field, there is the ability to specify more than 1 resource.

    When you increase the quantity, it should automatically reduce the run time. For instance, if the route is initially set to a process quantity of 1 unit per hour for 1 resource and you change it to 2 resources, it should reduce the run time to a 1/2 hour and keep the process quantity as 1.

    The only problem I see with this and your scenario is the scheduling engine will always split the production order across multiple resources. you would have to change the route on a single production order if you only want it to split in certain instances.

    Hope this helps

  • andhern15 Profile Picture
    36 User Group Leader on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Hi Victor

    I am having the same question. did you find any solution?

    Regards,

    Andrea H.

  • Community Member Profile Picture
    on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Hi Victor

    Did you find solution to your problem?

    I tried the below but it is loading only one resource ( I was expecting distribution of work to resources within the group).

    Resource group ( Calendar 8 hours)

                   Resource A ( Same 8 hour calendar) – Finite capacity – Capability A

                   Resource B ( same 8 hours calendar) – Finite capacity – Capability A ( both same capability)

    Item FG

                   Routing has only one step – needs 8 hours run time for one quantity

                   Capability required = Capability A ( which both the above resources have)

    Production order

                   Required 3 quantities

                   Run operation scheduling and Job scheduling

    Ax is only using one resource and using it for 3 days . whereas there is one idle resource with same capability which is not used.

    I was expecting the work to end in 2 days ( Day 1 – both Resource 1 and Resource 2 being used and Day 2 – Resource 1 only)

    Regards

    Jagabandhu

  • Rahul Shah Profile Picture
    2,696 on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Guys, anyone has a solution for this situation? I think this is a basic requirement for most of the organization and i believe there should be a way to achieve this. Any thoughts?

  • Suggested answer
    Muhammad Burhan Zahoor Profile Picture
    145 on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Hi Every one,

    Go to -> Production control->Common->Production orders->All production orders-> In Action Pane select Production Details -> Select Route -> In Resource Requirement tab Change the Quantity of Resources

    Multiple-Resource-Allocation.png

    Warm Regards,

    __________________________________________________________________________________________________________________

    Burhan Zahoor, Functional Consultant, Cell: +92 302 7792 6 40, Tel: +92 (42) 3520 3489-90 , Fax:  +92 (42) 3520 3485   Email: burhan.zahoor@maisonconsulting.com

  • Weaveriski Profile Picture
    23,616 Moderator on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    That does not really work, the question related to an exceeding of hours, but on no basis of the exceeding, perhaps capacity in a day, which would mean finite, but AX cannot dynamically add another resource, even within the group, as standard because an undefined amount of capacity has been used. The original post was basically if we have capacity of 8 hours on machine A today and the job takes 10 hours run the other 2 on the other resource. Adding in more resources would always split it, it is only when they need more based upon a capacity window would the second resource be needed. In most industries the planner looks at this and shifts lines etc.

  • Suggested answer
    hassanumair Profile Picture
    25 on at
    RE: how to schedule multiple production resources on same operation to reduce lead time

    Check last heading in below article, this might help you achieve your purpose

    community.dynamics.com/.../dynamics-ax-2012-production-control-tips-and-tricks-ii

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Pallavi Phade – Community Spotlight

We are honored to recognize Pallavi Phade as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Tocauer Profile Picture

Martin Tocauer 4

#2
AlissonGodoy Profile Picture

AlissonGodoy 2

#2
Nayyar Siddiqi Profile Picture

Nayyar Siddiqi 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans