I'd like to set up AX2012 so that scheduling will automatically add a second machine resource to the current operation when the required hours exceeds the capacity of the primary resource. In other words, minimize the lead time through production rather than stretch out the time using only one machine. I've tried this using a seconadry operation but AX just runs the secondary op for the same hours as the primary....it doesn't split the hours across both machines and thereby cut the clock time in half. Any thoughts?
*This post is locked for comments
Check last heading in below article, this might help you achieve your purpose
community.dynamics.com/.../dynamics-ax-2012-production-control-tips-and-tricks-ii
That does not really work, the question related to an exceeding of hours, but on no basis of the exceeding, perhaps capacity in a day, which would mean finite, but AX cannot dynamically add another resource, even within the group, as standard because an undefined amount of capacity has been used. The original post was basically if we have capacity of 8 hours on machine A today and the job takes 10 hours run the other 2 on the other resource. Adding in more resources would always split it, it is only when they need more based upon a capacity window would the second resource be needed. In most industries the planner looks at this and shifts lines etc.
Hi Every one,
Go to -> Production control->Common->Production orders->All production orders-> In Action Pane select Production Details -> Select Route -> In Resource Requirement tab Change the Quantity of Resources
Warm Regards,
__________________________________________________________________________________________________________________
Burhan Zahoor, Functional Consultant, Cell: +92 302 7792 6 40, Tel: +92 (42) 3520 3489-90 , Fax: +92 (42) 3520 3485 Email: burhan.zahoor@maisonconsulting.com
Guys, anyone has a solution for this situation? I think this is a basic requirement for most of the organization and i believe there should be a way to achieve this. Any thoughts?
Hi Victor
Did you find solution to your problem?
I tried the below but it is loading only one resource ( I was expecting distribution of work to resources within the group).
Resource group ( Calendar 8 hours)
Resource A ( Same 8 hour calendar) – Finite capacity – Capability A
Resource B ( same 8 hours calendar) – Finite capacity – Capability A ( both same capability)
Item FG
Routing has only one step – needs 8 hours run time for one quantity
Capability required = Capability A ( which both the above resources have)
Production order
Required 3 quantities
Run operation scheduling and Job scheduling
Ax is only using one resource and using it for 3 days . whereas there is one idle resource with same capability which is not used.
I was expecting the work to end in 2 days ( Day 1 – both Resource 1 and Resource 2 being used and Day 2 – Resource 1 only)
Regards
Jagabandhu
Hi Victor
I am having the same question. did you find any solution?
Regards,
Andrea H.
Hello Victor -
On the Route > Resource requirements tab > Quantity field, there is the ability to specify more than 1 resource.
When you increase the quantity, it should automatically reduce the run time. For instance, if the route is initially set to a process quantity of 1 unit per hour for 1 resource and you change it to 2 resources, it should reduce the run time to a 1/2 hour and keep the process quantity as 1.
The only problem I see with this and your scenario is the scheduling engine will always split the production order across multiple resources. you would have to change the route on a single production order if you only want it to split in certain instances.
Hope this helps
Thanks for the input. I have thought of what you are suggesting but it doesn't quite do what we need. We've already put the resources into a group....but the job scheduling engine only chooses one of the resources and it will run it as long as needed to get the job done. We'd like the scheduling engine to pick multiple resources, if available, so that the lead time is reduced.
Have you tried setting up a resource group? It's my understanding that if you have multiple resources doing the same function, you can combine them in a resource group, attach that group to the operation, and schedule capacity across the entire group.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,228 Super User 2024 Season 2
Martin Dráb 230,056 Most Valuable Professional
nmaenpaa 101,156