Hi,
I have installed AX + synchronization service on one server, and Project Server + synchronization proxy on another. When I'm trying to enable integration from "Microsoft Project Server integration settings" form, it gets stuck in "In progress" state. I noticed that whenever I click "Enable integration/Disable integration", this gets printed in the Event Viewer:
I followed this manual while installing the components: https://www.microsoft.com/en-us/download/details.aspx?id=15671
Any idea how to fix this?
Thanks!
*This post is locked for comments
I have the same question (0)Jack, Try this to see if it works:
1. Make sure your System Service Account for the synchronization is set to Admin.
2. Make sure the alias behind this UserID in the Users screen is Administrator.
3. Make sure the sync service and Project Server Event/Queue services Log On as Administrator.
Restart the machine (even if no changes were made in 1-3) and try again.
Hope this helps.
Bob Krajci