Hi guys..
I face a problem in creating Purchase Requisition.
I set a workflow for PR and it contain several steps, first submit > complete > approve and I set a control budget in PR
when I create a PR (submit > complete > approve) it works smoothly, however in PR list there is no green check mark so the PR can't move to release approved PR.
I tried to use Reserve budget fund menu in tab Financial, then the PR have a green check mark.
Is there a way to make the PR is automatically have a green check mark (without use Reserve budget fund) so I can continue the steps of procurement?
note: if I turn off the budget control, the process of procurement (PR submit > complete > approve until create PO) is work smoothly.
Is there any missing in setup budget or PR?