Due date changes suggestion to off hen using Planning worksheet

Posted on by 1,285

When calculating regenerative plan for production orders' requirement using planning worksheet, system always given suggestions regarding change due dates of existing production orders.

Can we make some configurations in system after which system will not give suggestions to change date of any production order.

*This post is locked for comments

  • Verified answer
    Saurabh Shah Profile Picture
    Saurabh Shah 4,560 on at
    RE: Due date changes suggestion to off hen using Planning worksheet

    Hi Ishan,

    Planning worksheet is always matching Demand Vs Supply with respect to demand date so if your supply orders (e.g. Production order, purchase order) due date is later than the demand date then system asking to change the dates of those supply order to meet the demand on time. however if you do not want to change the dates or do not want to have suggestion of changing the dates in planning worksheet then you can set planning flexibility of those supply orders as None.

    Planning flexibility is a field which is available on purchase order line as well as production line so if you set it as None then system will not suggest to change the dates of it however system will also not consider this supply against the demand order (e.g. sales order, production order component) and will suggest you to make new order against it.

    In case, if your supply order is earlier then the demand order then also system is suggesting to change the date later to exiting. you can overcome it by putting Dampener Period on item card.

    For more information about the supply planning in NAV 2013 please refer below link:

    msdn.microsoft.com/.../hh997394(v=nav.71).aspx

    Please let me know if you have any more question or please do verify this suggested answer if it solves your question.

    Regards,

    Saurabh Shah

  • Suggested answer
    Aleksandar Totovic Profile Picture
    Aleksandar Totovic 16,765 on at
    RE: Due date changes suggestion to off hen using Planning worksheet

    You cannot do it by default. But, I'm not sure what is your problem.

    When you run Calculate regenerative plan for the first time, system will suggest due date. If you change due date and change status of this Production Order to Firm Planed PO, system will not change your due date automatic. When you run again Calculate regenerative plan, system will suggest in Planning Worksheet to Cancel old PO and create New PO with new due date, but you have not to accept this. System will change your due dates only if you leave these POs in Planned PO status.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,232 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,064 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans