Production MRP Adding a lead time to a coverage / route / job planned item AX 2009

(0) ShareShare
ReportReport
Posted on by 355

We have a requirement that certain sub-assemblies be completed several days before their consumption into the next item up the BOM chain. We have tried adding lead times in the coverage plan and the item but the route overrides these values not changing the delivery date. Is there a way to add a buffer number of days to the delivery date and still use routes? 

Thanks for any help!

Konrad

 

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Community Member Profile Picture
    on at

    We did it by adding additional hours in the Queue time before and Queue time after fields on the route.  We also added additional days in the Issue margin on the Coverage groups.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans