Different between work center and machine center in this case proplem

Posted on by 4,548

Hi guys I have specified case proplem

I work in concrete readymix company have more branches.

my purpose from company produce ready mix concrete.

every company have more batch plant

you input gravel and cement and water and sand  to every batch planet as input  and output or result ready mix concrete.

My question here what i must added in machine center and what must added in work center

Example

Company A

Batch pant 1       Batch plant 2

                    car                                                              input                                   output                                             pump car

Supplier-----------------Sand - Gravel -Cement-Water------------------Batch Plant 1--------------------Readymix concrete------------------Customer

Customer sell ready mix

Which here represent work center and which represent machine center

Thanks

*This post is locked for comments

  • Suggested answer
    Aleksandar Totovic Profile Picture
    Aleksandar Totovic 16,765 on at
    RE: Different between work center and machine center in this case proplem

    The same question, the same answer :)

    This is very simply manufacturing model and you don't need 'Machine Centers'. Working with 'Work Centers' will be enough.

    You need to create 'Work Centers': Batch Plan 1, Batch Plan 2, Batch Plant 3...

    All of them need to have the same 'Work Center Group Code', because this is the same type of manufacturing.

    Because, this is the manufacturing of very same items on each WC, I advise you can configure 'Unit Cost Calculation' as 'Units'. This will make easy posting and you keep accurate cost calculation.

    In 'Direct Unit Cost' fields, you need to fill (after calculating) all cost (except material costs) per 'Unit Cost'.

    Other fields you can set by standard.

    You need to set independent 'Locations' for each WC. One for material and one for goods. In these material locations you will receive materials (sand, gravel, cement, but why water?) from your vendors, and in goods location you will put goods output before shiping to customers.

    I think this will be enough for start.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans