web
You’re offline. This is a read only version of the page.
close
Skip to main content
Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Answered

Forecast Models on Project Budget form

(0) ShareShare
ReportReport
Posted on by

Hi All,

I am trying to understand the logic behind having Original and Remaining budget fields in Project Budget form. I can understand that Original budget model is used to capture the original value but what does remaining budget mean and what information does it store?

Also while importing the budget - Total appears by default in import budget screen, what is the difference between total budget and original budget?

Regards,

Nakul

  • Suggested answer
    Ludwig Reinhard Profile Picture
    on at
    RE: Forecast Models on Project Budget form

    Hi Nakul,

    The remaining budget starts usually with the same qty and amount as the original one.

    The main difference is that it is automatically reduced as transactions are posted.

    This allows you identifying how much is left from the amount originally budgeted.

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at
    RE: Forecast Models on Project Budget form

    Hi Ludwig,

    Thanks for explaination, by D365 Product design - If I am not using forecast functionality still I need to select Original and Remaining budgets under forecast model, also while importing the budget from WBS, system asks for a budget model, does system store Original, Remaining and Total budgets somwhere in backend?

     I am not clear on the forecast model selection even if I am not using forecasting process.

    pastedimage1593333023124v1.png

    pastedimage1593333201996v2.png

  • Verified answer
    Ludwig Reinhard Profile Picture
    on at
    RE: Forecast Models on Project Budget form

    Hi Nakul,

    Many thanks for the screenprints.

    The budget related forecast models are special and different from what I referred to before.

    Its a bit related to the development of the project module and the things that were added later on, which makes things confusing.

    If you open the forecast model form then you will find your Original and Remaining forecast model. They are forecast models but have the type 'Original budget' or 'Remaining budget' assigned in the field called 'budget type'.

    Once you work with a WBS and transfer the values to your budget then you will have access to the tracking views that you can find in the control tab. Those view and the budget balance form that you can find in the same tab make use of the forecast-budget models and tell you what was originally budgeted and what is remaining.

    Agree that the design and naming convention is a bit 'special' but hope that you got the idea how and what they are used for.

    Best regards,  

    Ludwig

  • Community Member Profile Picture
    on at
    RE: Forecast Models on Project Budget form

    Thanks Ludwig for your response. I am clear on this point, but it sometimes beomes confusing even for clients to understand, I feel that nomenclature should be different for the models used for project budget

  • Suggested answer
    Ludwig Reinhard Profile Picture
    on at
    RE: Forecast Models on Project Budget form

    Hi nakul,

    Fully agree. The nomenclature is very confusing especially the mix of forecast and budget and models.

    Would be great if you could post a note on the dynamics experience forum to let MS know that this needs to be improved.

    Many thanks,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Pallavi Phade – Community Spotlight

We are honored to recognize Pallavi Phade as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans