Job Planning line splitting

(0) ShareShare
ReportReport
Posted on by 280

Hi Everyone.

Hope that all of you are keeping safe.

I am trying to split a job planning line for a job that i created but i am getting the below error message after running the "Split Planning Lines" batch job.

There are job planning lines that i have created for the related Job Task line.

pastedimage1611165328024v1.png

Please assist me on this.

Thanks and Warm Regards,

Denys De Andrado.

I have the same question (0)
  • Verified answer
    Community Member Profile Picture
    on at

    Denys,

    What does your Planning Lines look like for the Cost of Service Task? You can split the lines of the Both Schedule and Contract type into two

    separate planning lines: Schedule and Contract. Make sure you have a Planning Line with Both Schedule and Contract and it will split into 2 Planning Lines.

    Hope this helps.

    Thanks,

    Steve

  • Denys De Andrado Profile Picture
    280 on at

    Hi Steve,

    Thanks for the reply.

    These are the planning lines that are included in the job.

    pastedimage1611202357366v1.png

    Thanks and Warm Regards,

    Denys De Andrado.

  • Denys De Andrado Profile Picture
    280 on at

    Hi Steve,

    What i did was i deleted the splitted planning lines and i tried to resplit again.

    Then only i am getting that error message.

    Thanks and Warm Regards,

    Denys De Andrado.

  • Suggested answer
    Bilal Haider Profile Picture
    414 on at

    Hi,

    As Steven wrote that Splitting planning line function only works for a planning line of type Billable & Budget. It splits the line to two lines one as billable and other as budget.

    The message you are getting is not an error but a message that there is no Job Planning line that can be split.

    If you have removed the split lines then you should create a new line of type Budget & Billable and only then you can split again.

  • Suggested answer
    Community Member Profile Picture
    on at

    Bilal,

    Thanks for replying and updating.

    Denys - Hope this helps.

    Steve

  • Denys De Andrado Profile Picture
    280 on at

    Hi Bilal,

    Thanks for the help.

    Now i got it.

    Thanks and Warm Regards,

    Denys De Andrado.

  • Denys De Andrado Profile Picture
    280 on at

    Hi Steve,

    Thanks for the help.

    Thanks and Warm Regards,

    Denys De Andrado.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 3,151

#2
Jainam M. Kothari Profile Picture

Jainam M. Kothari 1,443 Super User 2025 Season 2

#3
YUN ZHU Profile Picture

YUN ZHU 1,092 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans