Is there any way to show Working, Booking, Non Working hours of Resource showed in grid or table form?
Is there any way to show Working, Booking, Non Working hours of Resource showed in grid or table form?
Hi Ashar.
The Schedule Board is the best option as Dan suggested. You also have the ability to print it.
If you need to list, you need to merge the Bookable Resource Booking, Time Entry and Appointment tables.
The Time Entry might give you what has gone and the scheduled holidays. The bookings and appointments give you what is coming.
How about the schedule board list view?
Hi Ashar Mustafa,
For Booking, you could create a tab and add a subgrid to achieve.
For Work Orders, you need to create a html web resource and use Web API to get them(Get all booking ids first and then get work orders). Finally insert the web resource to your form.
Non working hours can show on the Work Hours tab of Resource.
I have wanted to display on Resource Entity.
Hi Ashar Mustafa,
Where would you want to display these information and Working means work Order?