We have been using PSA for a couple of years and were looking forward to migrating to Project Operations soon, however the migration tool is now delayed to September which is a problem for us as our financial year ends on June 30th and we would like to start the new year on the new product.
So I have two questions:
Any thoughts or pointers would be appreciated.
Alister
Thanks Antti. I was fearful of this, most of our engagements are multi-year agreements with retainers and support for pre-payments is something we're really looking forward to. Currently we need to handle this manually using multiple contract lines and adjusting charging status for time entries each month, a process that is time consuming and exposed to error.
Hi Alister Grigg.
1. It's similar in ideas as PSA V2 to V3 was. No easy way to do this with any tools as you'd need to rebuild project schedules with the new scheduling APIs.
2. PSA and ProjOps can NOT co-exist in the same environment.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,232 Super User 2024 Season 2
Martin Dráb 230,064 Most Valuable Professional
nmaenpaa 101,156