What is impact of changing schedule mode from "fixed duration" to "fixed effort"

Posted on by 75

Hello Team,

Please let me know that impact of changing schedule mode from "fixed duration" to "fixed effort".

We have business scenario where effort is fixed but not duration. for example in one week duration task to be completed by 8 hours.

If I will change schedule mode from "fixed duration" to "fixed effort" of project, then it will change for new projects only. how about existing projects, should I change schedule mode for existing project also?

Thanks,

Vikas

  • Vikas P Profile Picture
    Vikas P 75 on at
    RE: What is impact of changing schedule mode from "fixed duration" to "fixed effort"

    Thanks Antti

  • Verified answer
    apa Profile Picture
    apa 8,282 on at
    RE: What is impact of changing schedule mode from "fixed duration" to "fixed effort"

    Hi Vikas P.

    Please see the following links for more information on the scheduling modes:
    https://daytodaydynamics365.com/scheduling-modes-in-project-operations-and-project-for-the-web/
    https://docs.microsoft.com/en-us/dynamics365/project-operations/project-management/scheduling-modes
    https://support.microsoft.com/en-us/office/how-project-schedules-tasks-behind-the-scenes-df3431ab-8d8a-4047-afc6-a87b547dbac0
    https://support.microsoft.com/en-us/office/change-the-task-type-for-more-accurate-scheduling-b0b969ad-45bc-4e9e-8967-435587548a72

    In a nutshell:

    • In fixed effort, effort is constant.
    • When duration is changed, units are recalculated.
    • It's only possible to set a scheduling mode for a NEW project. Scheduling mode for existing project can't be changed.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,269 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,198 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans