We have a project which requires producing 5 items from manufacturing. We are evaluating this in TEST. We are using a project item category "ProjItem" for testing. We require to charge 5 of these items once they are produced. We think the optimal methodology is to create a Production Order from the project for the 5 items. We wonder how once the Production order is created and then run and ended how to "bring" the financial transactions in to the project (ie charge the project with the 5 items ordered)? Any help (what the steps are) would be very welcome.
Thanks
Hi Simon,
The costs from the production order are visible as posted transaction on your project once the production order is completed.
The production process is thereby identical to a production that is not related to a project; that is you create the production order, start it, do the estimates, post the material and labor consumption, report it as finished and then end the production. Please have a look at the following docs site that describes the steps and transactions in more detail.
docs.microsoft.com/.../production-process-overview
Best regards,
Ludwig