Hi expert,
Currently I am working with the budget control setup. The scenario is to control budget quarterly with following conditions:
a. Original budget for all quarters within a year will be registered at once.
b. If the budget from previous month within the same quarter is never been used, then it will be accumulated for the next month.
c. If the budget for previous quarter is never been used, then the budget could not be carried over to next quarter.
d. Department cannot spend budget for a quarter at once in a month.
Scenario example:
Budget Original registered for Department A in period 2018:
Q1 = $120
Q2 = $120
Q3 = $120
Q4 = $120
Monthly budget for Department A is $120 / 3 = $40.
Condition expected:
- Department A cannot spend more than $120 in Q1.
- If the budget for January 2018 (Q1) is never been used by Department A, so in February 2018 (Q1) the budget for Department A is become $80 (budget Jan + budget Feb). Also, if budget for January and February is never been used by Department A then in March 2018 budget for Department A become $120.
- Department A cannot spend more than $40 in January 2018.
- If the budget from Q1 (Jan - Mar) is never been used by Department A, then in Q2 the Department A budget remains $120.
Is it possible to setup in Dynamic AX 2012 for that kind of scenario?