Dear All,
We have an issue in the production module. Every thing is working fine. We added the operation with link to resource (Machine).
We define the rate per hours and route is working fine. The cost is coming correct in the estimation, but when we are process the step "Report as finish", operation side in cost/price calculation column "Realized
consumption" showing double. we are using the backflushing for BOM and Routing.
This issue we are not getting in which parameter we selected or forget to avoid this issue. Can anyone elaborate this issue or guide us where we need to do the correction.