Hello,
Engineering staff have requested me whether it is possible for AX to convert processing time entered in min/kg to min/batch.
In order to achieve this I believe there must be two functions AX that I haven't got clue.
For No.1, I thought I could use formula size column on formula form, however it seems that formula size is used to scale composition of the constituent material.
For No.2, I though I could use "setting" tab>Formula on route form, where there is a option "batch". But I am finding that this option does not have any apparent effect.
I would greatly appreciate if you could give me a hint of achieving requirement from our engineers, as well as if you could share how does the forms described above should function.
Thank you in advance.
Sincerely,
ABTS
*This post is locked for comments
I have the same question (0)I could register bath size by "formula size multiple"
How could I register processing time per batch?