How does the unbudgeted cost works under Project management and accounting>>Project>>All projects>>Control tab in the action pane>>Unbudgeted cost?
When will this be updated?
I'm using D365 Project management and accounting.
Appreciate your replies.
Thanks.
Hello marypeace,
I would expect that you posted some costs on the project for which no budget amount has been specified.
If you allow budget overruns and are not very restrictive with the amounts that can be posted then you can see those unbudgeted costs.
Another reason can be if you post transactions on a main node in your WBS, i.e. on a summary node for which no budget has been recorded, rather than on the individual task elements setup in the WBS.
Best regards,
Ludwig
Thanks Ludwig.
I will simulate on that scenario wherein there are transactions posted but no budget amount has been specified.
Thanks Natalia.
Appreciate your input.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 646 Most Valuable Professional
André Arnaud de Cal... 529 Super User 2025 Season 2
Sohaib Cheema 285 User Group Leader