Start time and End time is not coming correct in Project WBS

(0) ShareShare
ReportReport
Posted on by 96

Hi,

I am creating a project task and the calendar attached to the project has working hours setup as 8am to 5pm with 1 hr break in between. Now when i am creating the project task and i set the duration as 1 days then system calculates wrong time on the start and end date field.

How it should work

Duration            Start date           End date 

1 Day                21 Oct - 8am      21 Oct - 5pm

How it is working

Duration            Start date            End date

1 Day                21 Oct - 9am       22 Oct - 9am

I have also attached the screenshot for reference.

pastedimage1634752291920v1.png

Regards

  • Suggested answer
    apa Profile Picture
    8,284 Moderator on at

    This is probably related to the same constraints that are described in this thread:
     

    Project for the web has heavy limitations in this area and they're not easy to understand or point out without Microsoft support clarifying expected behavior.

  • Suggested answer
    Gupta Kuldeep Profile Picture
    2,060 on at

    It is also based on the schedule mode setup in the Parameter settings as shown in the screenshot below.

    Read more about schedule mode settings from here Scheduling modes | Microsoft Docs

    Image

    Thanks,

    Kuldeep

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the August Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 507 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 419 Super User 2026 Season 2

#3
CU-1234529-002 Profile Picture

CU-1234529-002 155

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans