Hi all,
Having an issue with running master planning. Here's the scenario:
I have a sales order for item 07271 for 20 Units and there is are 2 in stock at the main warehouse on account of a transfer from another warehouse. If I update the master plan (static or dynamic) from the net requirements screen of the item, the planned purchase orders are created to satisfy the demand of 20 as well as increasing the inventory up to the max of 50 units.
Question #1: How do I adjust this to create one order for 68 units rather than 2 separate purchase orders?
If I then go to master planning > planned orders I see the orders listed above created and waiting to be firmed.
Question #2: As soon as I run master scheduling to take into account all demand (not just for item 07271), all planned orders are removed from the planned order screen. I've checked that filters are removed from the form etc... But I'm totally stuck on why the demand would be seen without issue from the net requirements but then not picked up when using master scheduling.
Any help would be really appreciated.
Thanks,
Simon
I've added in below some extra images to ensure the information you might need in helping me is available:
Master Plan Settings:
Item Coverage Settings:
Coverage Group General Settings:
*This post is locked for comments
I have the same question (0)

Report
All responses (
Answers (