Hello,
Like in project online there is allowed to modify % completion, but it is disabled in project operation. Is there is possibility that modify % completion in project operation?
Thanks,
Vikas
Hi,
The only way I have found to modify the % Complete on a Project task in Project Operations is on the tracking tab on a project. Here you can amend the "Effort remaining" field which updates the %Complete value.
KR
Mark
Mark is correct. Effort remaining changes % complete. It's also driven by approved time entries. In ProjOps the behavior of % complete is different than in vanilla Project for the web as the value in the column changes based on approved time and effort remaining.
thanks Antti
thanks Mark
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Pallavi Phade as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
André Arnaud de Cal... 747 Super User 2025 Season 2
CA Neeraj Kumar 743
Sohaib Cheema 528 User Group Leader