Hello Experts,
The pegging item is not automatically starting in parallel to the Main Production order. As you can see in this picture, the 3rd blue marked line is at the "scheduled" stage but the pegged orders are still in the "estimated" stage. So, I want to ask for any suggestions that can help me out with how to fix this issue. or is it a customization? Kindly give any insight.
Thank You.
Hi Ritesh,
First, this problem is not a customization.
Second, you can use update-> Operation schedule to schedule these two orders at estimated stage.
Third, remember to select the "Reference" option when scheduling the main order to avoid this inconsistency.