General journal posted transaction not recognized by project budget

(0) ShareShare
ReportReport
Posted on by

Hello Experts.

I have a general journal transaction posted successfully for a project , however surprisingly the project budget did not recognized this transaction ,i.e. got updated after these transactions were posted.

Project budget balance did not update after processing general journal adjustment , please suggest a fix.

System Ax 2012 R3. 6.3

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: General journal posted transaction not recognized by project budget

    Hello Mav,

    Many thanks for those details and the update on the R3 version that you operate.

    Can you provide some details on your project budget and how you set this one up?

    Did you use the project budget form, the project forecast form or the ledger budget to setup that one?

    Can you possibly share a screenprint/details of that?

    Many thanks,

    Ludwig

  • Mav Profile Picture
    on at
    RE: General journal posted transaction not recognized by project budget

    Scenario  & testing results.

    Project id proj1 total  project budget $1500.

    1>Posted a JE in GL JBN 1 with +-ve debit of  $500 for project category x . This created Projtransid1.

    Effect of posting above JE.

    a> Get a warning message like below.

    "This transaction causes the total cost budget for category x on proj 1 to be exceeded by $500 . The amount beyond the total budget will not be added to remaining budget"

    b> I can see the posted Projtransid1  & negative amt in Projtansposting table.
    c> I cannot see the same Projtransid1  as above in my projbudgetreductionhistory table, i think it should show there in order to cause effect on budget.

    d>Proj budget balance for category x remains unchanged , i.e. shows remaining budget for category x as $200

    2>Posted a JE in GL JBN2 with -ve debit of $500 for project category x , This created Projtransid2

    Effect of posting above JE.

    a> I can see the posted Projtransid2  & positive amt in Projtansposting table.
    b> I cannot see the same Projtransid2  as above in my projbudgetreductionhistory table also.

    c>Proj budget balance for category x changes shows remaining budget for category x as -$300.

    I cannot have remaining budget for category X as -$300 or total proj budget change from its orginal $1500. Please suggest a fix.

  • Mav Profile Picture
    on at
    RE: General journal posted transaction not recognized by project budget

    Please check below details of my versions , i think i have the latest version released on Feb 2019. Yet if you see i m missing any version please let me know the version i m missing from link below .

    Also kindly share the LCS KB you think i m missing, i will then check if that KB is installed already or not.

    https://cloudblogs.microsoft.com/dynamics365/no-audience/2012/03/29/overview-of-microsoft-dynamics-ax-build-numbers/

    2012r3versions.PNG

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: General journal posted transaction not recognized by project budget

    Good morning Mav,

    Your R3 version is already old. I just double checked the available hotfixes for project budget related issues on LCS and found many that seem to apply to your system version.

    Question: Is it possible that you upgrade to the latest R3 version or alternatively, that you go through the hotfixes available on LCS to assess which one you might have to install?

    Best regards,

    Ludwig

  • Mav Profile Picture
    on at
    RE: General journal posted transaction not recognized by project budget

    General Journal  1

    Offset account Proj 1 

    General  journal entry to debit offset account proj 1 with $500 , proj 1 is internal type.

    Proj 1 posted transaction shows $500 appearing in its list.

    Proj 1 budget balance should show $500 in its list but this $500 is missing in that list & hence budget is not increased by $500 which it should.

    Please let me know how why the posted transaction which is seen in posted transaction of project is not showing under proj budget balance & how to fix it.

  • Junaid Idrees Profile Picture
    on at
    RE: General journal posted transaction not recognized by project budget

    Hi Mav,

    Can you please clarify, what kind of adjustment you posted? And Did you post the transaction from Project accounting module or from GL module directly?

  • André Arnaud de Calavon Profile Picture
    294,099 Super User 2025 Season 1 on at
    RE: General journal posted transaction not recognized by project budget

    Hi Mav,

    Can you provide examples, e.g. screenshots what exactly was posted and how you found out that the budget was not updated?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge 🌸

WIN Power Platform Community Conference 2025 tickets!

Jonas ”Jones” Melgaard – Community Spotlight

We are honored to recognize Jonas "Jones" Melgaard as our April 2025…

Kudos to the March Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 294,099 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 232,866 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,158 Moderator

Leaderboard

Product updates

Dynamics 365 release plans