I am working on clearing a committed cost from a capital project, so I can create a fixed asset for the project, but I am unable to do so, since there is a committed cost. I looked up the PO that the committed cost is referencing, and there is no committed cost on the PO, usually if there's committed cost on the project, there is a committed cost on the PO, and if I clear the committed cost on the PO, it clears from the project. Can someone please advise how to clear the committed cost from the project that does not have a committed cost on the PO? I tried to finalize the line on the PO in a testing environment, but nothing happened to the committed cost on the project.