Hi Guys,
I want to clarify the concept about operation scheduling in AX.
Ex/
I have one resource group, RG
And RG consist of 2 resource, which is : RG01 and RG02 and have 8 hour working time per day for each resource
I have an item that have capacity 1 hour for 100 pcs in route
If I have sales order 2000 pcs for that item and then I run operation scheduling
My expectation is system will booked (reserve) capacity 2 day only.
16 hours in first day
4 hours in second day
Is that true?
Because in my testing, I’ve got 3 days
8 hours in first day
8 hours in second day
4 hours in third day
Regards,
EYO