Microsoft Dynamics NAV (Archived)

Unit Cost is not Updated

(0) ShareShare
ReportReport
Posted on by

Hello,

I got a problem on Item Card. Here is the detail:

On Item Card, the Costing Method is FIFO, Quantity on Hand is 20, but the Unit Cost is 0.

The Replenishment System is Assembly and it is "Make-to-Stock".

When I create an Assembly Order and fill out lines, the Unit Cost on Assembly Order is 0. After posting the Assembly Order, the Unit Cost on Item Card is still not updated.

Can anyone help me?  

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Alex A Profile Picture
    3,074 Super User 2026 Season 1 on at

    Have you configured your Bill of Materials and Routing(s) for this Assembled Item? If so, you can try the Calculate Standard Cost option from the Item Card.

  • Community Member Profile Picture
    on at

    Hi Alex,

    Thank you for your response. The Production BOM No. and Routing No. are blank field.

    Assembly_2D00_BOM.PNG

    Could you give more specific instructions? And How to configured Bill of Materials and Routing(s) for this item?

    Thank you!

  • Suggested answer
    keoma Profile Picture
    32,729 on at

    as alex suggests try to create a routing and a production bom for that item, then try again.

  • Community Member Profile Picture
    on at

    Hi Jonathan,

    Why do I need to create Production BOM? Or you mean Assembly BOM?

  • Suggested answer
    Alex A Profile Picture
    3,074 Super User 2026 Season 1 on at

    Hi Allen,

    You can find the Assembly BOM from the Item card on the Navigate tab, along with the Calc Standard Cost and Calc Unit Price functions.

    Also you'll need to learn about Work Centers/Machine Centers so you can then build your Routings. You can find all of these using the search bar at the top right of NAV. Depending on your manufacturing processs... you'll most likely need to set up at least a Work Center to use in your Routing for each Item you are producing (you may not need Machine Centers).

    After you create the Assembly BOM link it to the Item from the Item card; after you create the Work Center and the Routing, then link that Routing to the Item there on the Item card too.

    Regards,

  • Verified answer
    keoma Profile Picture
    32,729 on at

    in general field "unit cost" is not very informative. better use the statistics window.

    for calculation the item's "unit cost" follow

    msdn.microsoft.com/.../hh168041(v=nav.70).aspx

    when posting an assembly order the item's "unit cost" is not updated, but the fields "Rolled-up Material Cost" and "Single-Level Material Cost", because only material costs incur.

    additional follow http://dynamicsuser.net/forums/t/88057.aspx

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans