First, we run Lean AX2012 R3. I need to have kanbans that create after our fist shift to schedule on the next day - most are event kanbans.
I have set a calendar with work hours that stop at 2:30, which is shift change. I have set capacity at finite for the relevant workcells & master plan. I have used job scheduling. None of these settings impact the jobs, which are scheduled when the kanban triggers even though there are no working hours at the time, e.g. schedule at 3pm for the same day.
I tried adding a resource to the resource group with working hours that end at 2:30 - still no change. So, what am I missing or is there a bettter way of addressing this?