Hi All.
I have a master planning query. I have a client who generates no demand in AX. All of their commitment comes into master planning through a forecast.
Recently some of their demand dates have lapsed, and the requirement dates are in the past. Master planning now ignores these!
I have read up that forecast planning occurs ignores old demand by design. I can understand this, although in this instance, the forecast does represent actual commitment.
Is there a method to make master planning consider the whole forecast, or is the only method to fix the dates in the forecast?
Thanks
*This post is locked for comments
I have the same question (0)