Answered

Fixed Price project, and commercial invoice

(6) ShareShare
ReportReport
Posted on by 67
Hi, 
 
We are working on a case where we have Fixed price project agreements with our clients with milestone billing. The products need to be sent across various borders according to where the customers are placed. As part of this, we need invoice / commercial invoices for customs clearance. What would be the correct setup for doing this? We are working on a setup with a FP top project and TM sub project, however we are not sure if we miss a process path different from this. 
 
Cheers Daniel
I have the same question (0)
  • Adis Profile Picture
    6,048 Super User 2025 Season 2 on at
    Hi,
     
    For me its a bit hard to understand what part of the process is new and which parts are already in place. 
     
    Regarding Projects:
    Are you already working with projects? If so, which kind of projects (Fixed or TM or both)?
     
    Regarding customers aborad:
    Do you ship already items\services abroad, or is this something new?
     
     
    What I can tell you, the invoices you create are project invoices. Therefore, if you havent worked with projects so far you need to set up project invoice document as an ssrs report, through electronic reporting or a 3rd party ISV solution.
     

    Kind regards, Adis

     

    If this helped, please mark it as "Verified" for others facing the same issue

    Keep in mind that it is possible to mark more than one answer as verified

     
  • Daniel B KJ Profile Picture
    67 on at
    Hi @Adis
     
    Thanks for your reply. 
     
    We are transitioning from another ERP system, so no current processes are in place in D365FO. 

    The projects are FP in the agreements with customers. These projects include items that need to be sent abroad. The use of a TM sub-project would more be a way of achieving the commercial invoice - but it seems not optimal to go that way.  

    Yes, we have worked with Dynamics projects before. This issue is to have the FP projects with milestone billing while having a way to create the commercial invoice for logistics. The project invoice for milestone billing does not detail the prices of items, therefore we are looking for something different to support this. 
     
    Cheers
  • Verified answer
    Daniel B KJ Profile Picture
    67 on at
    For future reference, we found the solution by using the advanced WH module on Item requirement lines for a FP project. Thereby, we don't need to use TM project. 

    The advances WH, can support the logistic documents on shipment / loads. Im not sure when this was availble, but glad to see it now. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 660 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 549 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 307 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans